This site was created by ordinary school district residents, just like you, who are investing their own time and money to raise public awareness. They are concerned that the Superintendent and School Board are trying to push through a quarter of a billion dollars of spending over 35 years before the public learns about the cost, the flimsy rationale, and the alternatives.

Update Fall 2026 – Project Cost Increased to $171MM. District Moving Forward with another $5MM for Detailed Design Despite Deficit. Cost to Every Taxpayer ~$40,000 over 35 years

November 10, 2026

A member of the UCFSD community has done a detailed analysis of the cost estimates provided by the District for the new Middle School.   His work indicates that if calculated using industry standard estimating methodology, the cost for the project would be $6 milllion higher.  Consequently, the total project cost should be seen as $171 million vs. the already massive $165 million put forward by the District, which vastly exceeds the $120 million in the original plan.  He calls this to the District’s attention in the attached memorandum.

This original $120MM plan was to be creatively financed in 6 borrowing tranches over 35 years for $140MM of interest, or $260MM total. Now that the $120MM construction cost has become $171MM, if we assume the same relative borrowing cost, that $171MM will cost us another $200MM to finance, bringing the total project cost to around $370MM. There are roughly 9400 taxpayers in the school district, so your share is almost $40,000 (over ~35 years).

Despite the prohibitive cost, the District appears to be plowing ahead with the project, even thought they have conducted NO analysis of the borrowings that will be required and the impact on future tax rates.  While trumpeting “fiscal responsibility,” the Administration and Board are failing in even the most basic tenets of responsible of financial management.  Based on discussions at last week’s Board workshop, they aren’t even sure how large the building should be, yet plan to vote on  funding detailed design at tomorrow’s regular Board meeting.

I again urge you to make known to the Board your thoughts about their headlong rush to proceed with this project before basic questions are answered and with no real communication with residents.  Email them at ucfboard@ucfsd.net or attend tomorrow’s meeting (7:30 pm at the District Office – the south end of the Unionville High School 750 Unionville Rd, Kennett Square, PA 19348).

MEMORANDUM

TO: Unionville-Chadds Ford School District Board of School Directors

FROM: <School District Resident>

CC: Dr. Timothy Hoffman, Superintendent of Schools; Joseph Deady, Director of Finance and Board Secretary; James Whitesel, Director of Facilities, UCFSD Solicitor

DATE: November 13, 2026

SUBJECT: Fiduciary Risk Alert: Structural Estimating Discrepancies in Middle School Project

A detailed review of the recent cost estimate prepared in October 2026 by ICS-CMTA for the UCFSD Middle School project has revealed severe methodological flaws. With construction slated to begin in early 2032 and complete in 2033/2034, accurate long-term financial forecasting is critical. Unfortunately, the current estimate fails to utilize standard compounding formulas for escalation and miscalculates critical contingencies, resulting in an artificial deflation of the project budget by more than $6 million.

When the Board elected to hire ICS-CMTA, it explicitly carved out the responsibilities of an Owner’s Representative. The stated intent was to secure an independent advocate who works directly for the Board to protect the District’s financial interests, prevent scope creep, and ensure absolute transparency. The current estimating methodology and subsequent lack of responsiveness from ICS-CMTA run directly counter to this mandate, leaving the District exposed to severe, unbudgeted financial liabilities when actual bids are ultimately received.

Deviation from Standard Estimating Methodology ($6M+ Variance) Capital construction estimating relies on established industry standards (including those from AACE, ASPE, PMI, GAO, and CMAA) to protect owners from market volatility over multi-year timelines. The ICS-CMTA estimate violates these standards in several critical ways:

  • Failure to Compound Escalation: Construction escalation acts similarly to interest; it must be compounded annually over the life of the project. The current estimate applies a simple, flat escalation rate to the baseline cost rather than compounding it over the 6-to-8-year timeline, mathematically underfunding the out-years of the construction schedule.
  • Static and Miscalculated Contingencies: Contingency pools exist to cover the unknowns in a project. As the base cost of the project inflates over time, the contingency must escalate proportionally to maintain its purchasing power. ICS-CMTA excluded contingencies from the escalation model entirely.
  • Flawed Construction Contingency Baseline: ICS-CMTA calculated the Construction Contingency strictly against the raw baseline cost, completely omitting the Design/Estimating Contingency and all escalation from this calculation.
  • Unexplained Baseline Reductions: ICS-CMTA has reportedly reduced the amount of the baseline cost that is subject to the Design/Estimating Contingency. The exact amount of this reduction has not been specified, and no explanation has been provided despite multiple inquiries.

Combined, these structural flaws create a hidden budget deficit in excess of $6 million. If left uncorrected, the District will be forced to execute drastic, painful value engineering—likely cutting core educational program spaces and facility quality—late in the design phase to compensate for this artificial deflation.

Lack of Transparency and Communication I have formally called these specific methodological and scope discrepancies to the attention of the project team and requested a technical explanation for their departure from recognized industry standards. To date, I have not received any explanation or justification. An Owner’s Representative cannot operate effectively while ignoring material financial inquiries.

Recommended Board Actions To uphold its fiduciary duty to the taxpayers and ensure the Middle School project remains viable, the Board should immediately direct the following actions:

  1. Compel a Formal Response: The Board must require ICS-CMTA to publicly explain, in writing, why they have deviated from standard compounding escalation and contingency calculation practices.
  2. Commission a Third-Party Peer Review: Authorize a brief, independent peer review of the ICS-CMTA estimate by a separate, qualified construction estimating firm. This is a low-cost, standard industry best practice that will definitively validate or correct the current math before the District officially commits to a budget.

I am available to provide the detailed mathematical breakdown of the $6 million variance at the Board’s convenience.

November 10, 2026 – UCFSD Board Plowing Ahead with New Middle School Despite Deteriorating Finances

At last night’s UCFSD Board work session meeting, the Administration stated that next week, it will ask the Board to approve the Schematic Design for their new, $165 million middle school project.  This means that detailed design for the new school will begin immediately, with expected spending of $5-6 million over the next two years.  This is the first major decision that will lead to a $165 million building that the District doesn’t need and the taxpayers can’t afford.

Please see attached below the note I just sent to the School Board.  Please also see the article from Chadds Ford Live (link attached). https://chaddsfordlive.com/2026/11/ucf-to-vote-on-middle-school-project/

The Board is moving forward with a much changed, and vastly more expensive (38% more costly) project than the $120 million project we saw last year.  There have been no substantive financial analyses or communications about it.  The District is in difficult financial straits (ended last year with a deficit that greatly depleted the remaining reserves) yet continues to press on.  District officials need to hear from taxpayers that (1) the project has not been adequately justified and is far larger than enrollment projections require, (2) the District needs to complete basic financial analysis about its impact on the District and taxpayers–this is their fiduciary duty, and (3) the District needs to seek public input for this plan before moving forward.  There has been essentially no communication about the project this year, and it has changed markedly.  It appears almost certain that the project will now require a voter referendum, and District officials need to hear that the project is unlikely to be approved if they stay on their current path.

Sent: Tuesday, November 10, 2026 1:46 PM
To: [District Office] Board Members <ucfboard@ucfsd.net>
Subject: Middle School project: not ready to move ahead

Based on the discussion at the work session yesterday, it appears the Administration is targeting approval of the schematic design (SD) of the Middle School project at next week’s Board meeting, allowing detailed design to begin immediately.  Based on previous information, the detailed design will cost $5-6 million over the next two years.

UCFSD is driving the project forward despite the following major unaddressed issues:

  • Uncertain scope.  Board members suggested that given the flat to declining enrollment projections, a new school with an effective capacity of 1200 students may be too large and too expensive.  Enrollment is projected to decline from 865 currently to 799 in a decade.  They suggested that a smaller scope might make more sense.  Of course, if the SD is approved, detailed design on the larger scope will begin.  The cost of this work could be wasted.
  • Financials. The Administration has provided no financial analysis of how the project will be funded.  How much will be borrowed, and when?  What credit rating can be obtained, given the continued poor financial performance of the district and the depletion of its unassigned fund balance? What will be the resulting interest rate?  What tax increases will be required?  How much will it cost the average taxpayer?  It is hard to imagine moving ahead without this basic financial analysis.
  • Communications. The District has done nothing substantive to communicate the current status of the project.  The Middle School project page of the UCFSD website is devoid of information.  There have been no meetings, emails, or mailings.  The last details the public heard from official channels was that UCFSD was building a new middle school costing $120 million (which the previous superintendent stated was the maximum UFSD could afford).  Now the District is moving forward with a $165 million project on a significantly delayed timeline, and there has been no effort to communicate this, and the rationale for it, to the community.
  • Act 34 and Act 1. While we don’t have all the details, we can be quite confident that the District will be required to seek voter approval under both Act 1 and Act 34.  In the past, some Board members have stated that they would be uncomfortable doing this, yet there has been no discussion about the need for a referendum since the project has been redefined.  Keep in mind that Act 34 is known as the “Taj Mahal Act.”   Receiving voter approval for a “Taj Mahal” project that has been launched (in its latest incarnation) with no public input and builds a new middle school that (1) provides ~50% more capacity than the District’s enrollment projections require and (2) has 17% more square footage, and 4% less capacity, than the existing school, will be difficult indeed.  You can be sure that many unhappy residents will point out these things, and others, to the voting public.

By proceeding with the project under these conditions, the District is courting a fiscal and public relations disaster.  The Board needs to pause the project and:

  • Have a deep and detailed discussion about the scope of the building really required
  • Do the detailed financial analysis required to understand the financial consequences of this project on the District and its taxpayers.
  • Communicate with the public and seek their input before proceeding with a “Taj Mahal” project that is massively more expensive than previously communicated.  Put this in the context of a District that is facing much greater financial challenges than anticipated.

Please let me know if you have any questions or would like to discuss further.

Mark

October 15, 2026 – Surprise! The UCFSD budget swung to a $2.7MM Deficit this year

Over the weekend, UCFSD published a “budget update” revealing that instead of roughly breaking even during the last fiscal year (ending 6/30/2026), the District ran a $2.7 million deficit. Similarly, the budget for the current year, which was supposed to be balanced, is now expected to show a deficit of $1.9 million. The District’s unassigned fund balance (reserve) is only about $5 million, so they are essentially using up all of their cushion. Their Board policy requires them to maintain a fund balance at the $5 million level (5% of their $115 million in revenue), and the credit rating agencies are concerned that even that is too low.

The October Budget Update (below) says that the school district administration is doing a great job, but bad things are happening externally and causing deficits.  They blame their problems mainly on special education costs, but their analysis is just flat out wrong because the state allows them to exceed Act 1 limits if special ed costs exceed inflation.

The administration has no explanation for how the deficits suddenly emerged and no plan for dealing with them. It’s clear that UCFSD is in no way ready to implement a $160 million project for a new middle school from either a leadership or financial standpoint. It’s amateur hour.